Quick answer: Concrete is worked out by volume: length × width × depth. A slab 2m × 2m × 100mm needs 0.4 m³ of concrete. To make that yourself you’d need roughly 0.4 m³ × 1.8 = 0.72 tonnes of ballast plus cement at a 1:5 mix, or you can order 0.4 m³ of ready-mix. Always add about 10% for spillage, uneven ground, and coming up short. Over about 1 m³, ready-mix delivery is usually easier than mixing by hand.

Whether you’re laying a slab, a shed base, footings, or a path, the concrete calculation is the same — work out the volume, then decide whether to mix it or order it ready-made. Getting the volume right and adding a sensible margin is what stops you running short mid-pour, which risks a weak joint. This guide covers volumes for common projects, mixing versus ready-mix, and how much extra to allow. Use the calculator above to work out your volume.

The basic calculation

Concrete volume is length × width × depth, all in the same units. Keep depth in metres: 100mm is 0.1m. Some common projects:

Project Dimensions Volume
Small slab 2m × 2m × 100mm 0.4 m³
Shed base 3m × 2m × 100mm 0.6 m³
Path 10m × 0.8m × 100mm 0.8 m³
Strip footing 10m × 0.3m × 0.4m 1.2 m³

For an L-shape or irregular area, break it into rectangles, work out each volume, and add them together. For post holes and footings, it’s the trench or hole volume (see our fence-post and ballast guides for those specifics).

Mixing your own vs ready-mix

Once you have the volume, you choose how to supply it. Mixing your own from ballast and cement (around a 1:5 mix) is cheapest for small volumes and gives you control, but it’s hard work and slow for anything large. Ready-mix delivered is easier and more consistent, and usually the better choice above about 1 m³ — mixing that much by hand or in a small mixer is a serious undertaking, and a large pour needs to go in continuously to avoid weak joints between batches.

As a rough dividing line: under about 0.5 m³, mix your own; 0.5–1 m³, either works depending on how much effort you want; over 1 m³, seriously consider ready-mix. A slow hand-mixed large pour risks setting between batches, which weakens the finished concrete.

How much ballast and cement if mixing

If you’re mixing your own, to make 1 m³ of concrete at a general 1:5 mix you need roughly 1.8 tonnes of ballast and about 6–7 bags of 25kg cement. Scale to your volume: a 0.4 m³ slab needs about 0.72 tonnes of ballast and 3 bags of cement.

Remember the raw materials add up to more than the finished volume, because fine particles fill the gaps as the mix compacts — so you always buy for a bit more than the neat volume figure suggests. The calculator gives your concrete volume; multiply by 1.8 tonnes/m³ for the ballast.

Always add a margin

Add around 10% to your calculated volume. Ground is rarely perfectly level, so a “100mm” slab is deeper in the dips; some concrete is lost to spillage and the mixer; and coming up short mid-pour means either a rushed extra batch or a cold joint where fresh concrete meets partly-set concrete, which creates a weak plane. For ready-mix especially, it’s worth erring up, since a second delivery for a small shortfall is expensive and slow.

So a 0.4 m³ slab becomes about 0.45 m³ ordered. The small extra is cheap insurance against a weak or unfinished pour.

Get the base and formwork right

Concrete needs a solid, level base and containment to set properly. Lay it over a compacted sub-base (MOT Type 1) on soft ground so it doesn’t crack and sink, and set formwork (timber shuttering) to hold the concrete to the right shape and level while it sets. For slabs and bases taking weight, adding reinforcement (mesh or rebar) helps prevent cracking. These aren’t part of the concrete volume but they’re part of getting a lasting result, so plan them alongside the pour.

Common mistakes to avoid

The main mistakes are under-ordering and running short mid-pour, hand-mixing a large volume that should be ready-mix, forgetting the 10% margin for uneven ground and spillage, and pouring onto soft ground with no sub-base so the slab cracks. One more: mixing too wet — a sloppy mix is easier to work but sets weaker, so keep it to a workable, not runny, consistency.

Frequently asked questions

How do I calculate how much concrete I need?

Multiply length × width × depth in metres for the volume — a 2m × 2m × 100mm slab is 0.4 m³. Break irregular shapes into rectangles and add them. Then add about 10% for uneven ground and spillage before ordering or mixing.

How much ballast and cement for 1m³ of concrete?

Roughly 1.8 tonnes of ballast and 6–7 bags of 25kg cement at a general 1:5 mix. The raw materials exceed the finished volume because fine particles fill the gaps as it compacts, so allow a little extra.

Should I mix my own concrete or order ready-mix?

Under about 0.5 m³, mixing your own is cheapest; over about 1 m³, ready-mix delivery is usually easier and avoids weak joints from slow hand-mixing. Between the two, it depends on how much effort you want to put in.

How much extra concrete should I order?

About 10% more than the calculated volume, to cover uneven ground, spillage, and the risk of running short mid-pour. A shortfall means a rushed second batch or a weak cold joint, so erring slightly high is worth it.

Do I need a sub-base under concrete?

On soft ground, yes — a compacted MOT Type 1 sub-base stops the concrete cracking and sinking. Firm, stable ground may need less, but most slabs and bases benefit from a proper compacted base beneath the concrete.

How thick should a concrete slab be?

For a garden slab or shed base, around 100mm is typical; for areas taking heavier loads, thicker with reinforcement. The depth goes straight into the volume calculation, so a thicker slab needs proportionally more concrete.